Hawthorne Residence
MK
Operational signals3 overdue selectionsLighting package at riskTile lock deadline in 12 days

Whitaker Family · 1408 Hawthorne Lane · Aspen, CO

One quiet place for every decision that builds the house.

Completion
62%
Phase 4 of 9 · Framing
Pending decisions
7
3 overdue · 4 awaiting client
At-risk selections
3
Lighting & marble lead times
Budget delta
+$58,700
$617,300 of $558,600 allowance

Upcoming lock deadlines

Sorted by schedule risk
  • Appliance Suite
    Kitchen · locks before Rough-In
    26d overdue
  • Range Hood
    Kitchen · locks before Rough-In
    26d overdue
  • Lighting Package
    Whole House · locks before Rough Electrical
    8d overdue
  • Powder Sconces
    Powder · locks before Rough Electrical
    8d overdue
  • Primary Tub
    Primary Bath · locks before Rough Plumbing
    3d
  • Primary Faucets
    Primary Bath · locks before Rough Plumbing
    3d

Operational pulse

Approved5 / 24
Ordered3 / 24
Installed2 / 24
At risk3 / 24

Selections at risk

  • Calacatta Marble Slab
    Ann Sacks · 6w lead · locks before Tile
    At risk
  • Lighting Package
    Apparatus Studio · 12w lead · locks before Rough Electrical
    Overdue
  • Stair Railing
    TBD · 10w lead · locks before Trim
    At risk

What's quietly working

Selections that are sequenced correctly, on schedule, and within allowance. No action required.

White Oak Flooring
Appliance Suite
Kitchen Faucet
Cabinet Hardware
Powder Room Vanity
Exterior Sconces
Mudroom Tile
Wine Room Glass